Photos

Plans for this East Horseley property
Plans for this East Horseley property
Plans for this East Horseley property
Just a quick picture to show the property with the old roof removed, prior to the attic trusses being craned into place.
Truss roof ready to be craned in.  Job is in East Horseley
Attic trusses being spread to correct positions.
Truss roof now spread and barn ends are cut in.  Spaces are for the dormers.  A lot of work goes into these roofs
Just to show the barn ends being cut.  Blockwork will be bricked up underneath the plate
Dormer being framed out from above
Making a start on framing the dormers
Hipped roof dormers under construction
Hipped roof dormers under construction
Hipped roof dormers under construction.  As you can see the ply cheeks are now on and are starting to take shape
Flat roof joists in place spanning from steel to outside wall.  Also you can see the opening framed out for the roof lantern
Hipped roof dormers ready for fascia
Roof being tiled in
Roof now being tiled
Lead work to dormer cheeks
Roof being tiled, also just to show the barn end as well
Flat roof now boarded ready for torch down felt.  Aslo the upstand is in for the roof lantern.  Good progress on the roof tiling as well
Roof tiled and dormers complete.
Flat roof now boarded ready for torch down felt.  Aslo the upstand is in for the roof lantern.  Good progress on the roof tiling as well
Flat roof completed and ready for installation of glass roof lantern
Just to show progress now the scaffoldng has been dropped
Caberdek flooring being laid to first floor. First part of the first fix is now under way
Dave making a start on the first floor studwork
First floor studwork almost complete.
Counterbattening the ceiling to allow for cables and pipes to be run
Ground floor first fix studwork well under way. As you can see the ceiling has had to be counterbattened to allow cables and pipework to be run. Truss roof forms the
Ground floor first fix studwork well under way. As you can see the ceiling has had to be counterbattened to allow cables and pipework to be run. Truss roof forms the floor above
Stairwell framed out ready for the staircase
Insulation added to studwork prior ro plasterboard
First floor has now had the first fix completed.  Electrics and plumbing have been run, and now its been tacked.  Really starting to take shape
All stud work complete to the first floor. Almost ready for plaster
Staircase fitted prior to handrails and spindles
Room prior to Day Crapentry installing ktchen, flooring and completion of second fix.  This property is in East horseley
Delivery of lamite flooring ready to go down.  As you can see its the entire ground floor so plenty ro get on with
Staircase installed and protected on the treads with Corex
Staircase installed with balustrading completed.
2nd fix underway at this East Horsley property.  Doors being hung and architrave being fitted
First floor 2nd fix completed.  Decorating has been finished and carpet has been laid
Built in wardrobes to first floor in East Horesley property
Kitchen being installed. As you can see this open plan design with roof lantern really makes this a beautiful place to have the kitchen
Base units fitted, just working on getting the wall units mounted.  Will look great when its finished
Kitchen starting to go in
Kitchen almost completed. Client was starting to get excited at this point
Utility room now completed
Kitchen completed with curved base unit.  Wall units matches above. Plinth lights have been added for that extra bit of style
Kitchen now fitted.  This customer decided that white worktops would look best and I have to agree. Stunning looking kitchen
Laminate flooring being laid
Laminate floor being laid
Floor and second fix on groundfloor now completed